- Original contract sum from the signed estimate or contract.
- Prior change orders already approved (running total of adds and deducts).
- This change as a priced add or deduct with a short description.
- Revised contract sum after this change.
Put all four on the PDF before work starts. Long how-to: change order form. Outcome rule: sign before extra work.